Progress claim reconciliation: what to inventory before a commercial system migration

Short answer

Before a commercial system migration, inventory the three records that explain each progress claim: the measured work from project controls, every version of the claim as submitted and revised, and the certified amount booked in the ERP. Note which system holds each, the projects and years covered, who owns them and the date old access ends. Then introduce the executive who can authorize a data discussion; whether the records can be licensed depends on rights, qualification and the proposed use.

Visual briefFull-size diagram
A tree from claim history to three systems: project controls holds claim versions and measured quantities, the ERP holds certified amounts and retention events, and correspondence holds certificate reasons; certified amounts and retention survive the migration, the other three are at risk.
Illustrative record tree for a fictional contractor before a commercial system migration; each company's systems will differ.

Progress claim reconciliation is the monthly work of matching what a contractor claimed against what was measured on site and what the client certified. The gap between those three numbers, and the reasons recorded for it, is the history worth protecting. A commercial system migration rarely protects it by default, because the new ERP or project controls platform needs open contracts and balances, not the argument behind last year's certificate.

What should be inventoried before a commercial system migration affects progress claim reconciliation history?

Record classes, time coverage, system owners and the real access deadline, grouped by the system that holds them. A construction accountant usually sees the risk first: a new ERP or project controls platform goes live, and only open contracts and closing balances are migrated.

Project controls (or the claim workbooks)

  • ☐
    Every submitted version of each claim, not only the latest
  • ☐
    Measured quantities, progress photos and inspection dates per line
  • ☐
    Years and number of closed projects still held

ERP

  • ☐
    Progress invoices with claim and certificate references
  • ☐
    Certified amounts, retention and release events per contract
  • ☐
    Whether closed jobs migrate in detail or only as opening balances

Correspondence and contracts

  • ☐
    Certificates or payment schedules with stated reasons
  • ☐
    Quantity surveyor or client queries on disputed lines
  • ☐
    Head contract confidentiality clauses

Ownership and timing

  • ☐
    Who administers each system, and who decides retention
  • ☐
    The date read access to the old system ends, from the contract or the migration plan

A partner records the answers, not the records. Do not collect exports, logins or certificates, and do not advise the company to keep data beyond its own policy or authority.

Why claim history is the part a migration drops

Because the three numbers live in three places, and a migration is planned one system at a time. Claim versions are often workbooks exported from project controls. Certified amounts are booked in the ERP. The reasons for any difference sit in certificates, payment schedules and email.

Payment rules explain why those reasons usually exist in writing. Under FAR 52.232-5, progress payments on U.S. federal fixed-price construction contracts are made monthly or more often on estimates of work accomplished that meets contract quality standards; requests must be substantiated and carry a contractor certification, and up to 10 percent may be retained when progress is not satisfactory. In New South Wales, a respondent must serve a payment schedule within the contract time or 10 business days, whichever is earlier, stating the scheduled amount and the reasons if it is less than the amount claimed. A company that has worked under rules like these for years usually holds a long, dated record of claims, reductions and reasons. Whether it can still be read after the migration is the question.

Retention adds a timing trap. FAR 52.232-27 makes progress payments due 14 days after a proper payment request reaches the designated billing office, while retained amounts follow a separate timeline. A project can be closed for billing but still open for retention, so ask whether the migration treats those jobs as open, closed or split.

An illustrative inventory sheet

Illustrative only; the company and figures are fictional. A 340-person building contractor is moving its claims into a new project controls platform; its ERP stays in place. Its construction accountant fills in the sheet with the commercial director in one meeting.

Record classSystemYears heldOwnerMoves at cutover?Readable until
Claim versionsOld project controls platform2015 to nowCommercial directorLatest version for open jobsOld platform license end
Measured quantities and inspectionsOld project controls platform2017 to nowProject controls managerOpen jobs onlyOld platform license end
Certified amountsERP invoice history2014 to nowFinancial controllerNot affectedERP kept
Retention and release eventsERP2014 to nowFinancial controllerNot affectedERP kept
Certificate reasons and queriesEmail, document control2016 to nowCommercial directorNoMailbox retention policy

Reading the sheet: the money survives, because certified amounts and retention stay in the ERP. What explains the money does not: earlier claim versions and measured quantities depend on the old project controls license, and the reasons sit in email under its own retention rule. The handoff should name both dates.

Which date is the real deadline?

The earliest of the read-access end dates: the old project controls license, any ERP read-only period if the ERP is also being replaced, and the mailbox retention rule for correspondence. Go-live of the new platform is usually earlier than all of them and matters less. If the company has not fixed a read-only period yet, record "not set" rather than estimating one.

Who decides, and does the company qualify?

The construction accountant and commercial director know coverage. The CEO, CFO or managing director decides whether a licensing discussion fits, and counsel checks head contract confidentiality and any government contract limits.

The introduced company needs 50+ full-time employees at peak (contractors excluded), a documented operating history, rights to license the records, and an authorized contact. Companies in the U.S., Canada and the EU qualify, as do companies in the UK, Australia, New Zealand, India, Singapore, South Africa, Latin America, the UAE and Saudi Arabia when at least 90% of the data is in English.

What stays unknown until SourceX reviews it: dataset demand, the rights review result, what must be removed and whether any offer follows. Partners sign the Channel Partner Agreement before submitting introductions, and the first valid introduction within the 90-day window is credited when the company submits a verified application. Related record types: pay application review, change order data, reconciliation exceptions and the industries hub.

Go deeper on progress claim reconciliation

Next step

Refer a company. Earn up to $100,000. Default reward: 25% of Actual Supplier Payout, capped at $100,000 cumulatively per referred company. Eligibility and payment conditions apply, and a signed Schedule A or addendum can differ. A lead, meeting or signature alone does not trigger payment.

If a client is migrating its ERP or project controls and years of claim history will not move with it, register as a partner, check the company against who qualifies, and read the program terms before you send the one-page handoff.

  1. Step 1Share your linkSend your personal link to a company you know.
  2. Step 2Company appliesThe company applies itself at /apply.
  3. Step 3Company signs and is paidThe company signs, delivers its data and is paid by SourceX under its agreement.
  4. Step 4You get your rewardYour 25% of the actual supplier payout. A reward becomes payable after SourceX has paid the referred company under its signed agreement and the payout conditions in the program terms are met, including finance approval and your tax and payment details.

Common questions

Is a progress claim the same as a pay application?

They describe the same monthly event from different traditions. Progress claim and payment claim are common in Australia, New Zealand and the UK; pay application is common in the U.S. The records behind them, measured work, claim versions and certified amounts, are similar.

Can a contractor license records about a client's project?

Only as far as its contracts and the law allow. Head contracts often include confidentiality clauses, and government work can carry extra limits. SourceX runs a rights review before anything is licensed, so a partner only notes that the question exists.

Does the partner need to see claim spreadsheets?

No. A partner records which systems hold the claims, how many projects and years they cover, and who owns them. Spreadsheets, certificates and ERP exports stay with the company.

Sources

  1. acquisition.gov/far/52.232-5
  2. acquisition.gov/far/52.232-27
  3. nsw.gov.au/housing-and-construction/compliance-and-regu…
  4. refer.sourcex.si/terms

Free resources

Know a company with valuable proprietary data?

Become a referral partner, get your link and introduce the company’s CEO (in an owner-run company, usually the owner). Referral partners can join from most countries. We can't work with partners in countries or regions under U.S. sanctions or on U.S. restricted-party lists. The companies you introduce should be based in the U.S., Canada and the EU, or in the UK, Australia, New Zealand, India, Singapore, South Africa, Latin America, the UAE and Saudi Arabia with at least 90% of their data in English.

Refer a company →

I own a business

Explore licensing your company's data directly to SourceX for AI training and evaluation. Start a short assessment; no uploads needed.

Start an assessment