Scope creep adjudication, a worked hard case: how a weekly favor became a change order

Short answer

The scope creep records that explain an exception show four things in order: the original commitment, the informal request that broke it, the decision someone made about it, and what happened afterwards. In practice that means the signed SOW versions, the client's request, the time logged against the work, the change request with its approver and reason, the amended SOW and a later note on the outcome. A change order alone shows a price; the full chain shows why the firm chose it.

Visual briefFull-size diagram
A case timeline from a signed SOW on February 3 that branches at a March 11 client email: the hidden path logs 72 hours to a support task, then a June 4 change request leads to the June 9 split decision (72 hours absorbed as goodwill, future hours billed), SOW version 3 on June 16 and a renewal noted September 30.
Illustrative. A fictional IT consulting engagement; dates and hours show the shape of one adjudicated exception.

This worked case is part of the scope creep adjudication guide, which covers what to inventory before a PSA migration. Here the job is to walk one hard case end to end, so a professional services automation consultant can recognize the same pattern at a client.

The engagement before anything went wrong

Illustrative only. A 180-person IT consulting firm runs a fixed-fee data platform engagement for a regional retailer. SOW version 2, signed on February 3, covers the platform build plus 120 hours of handover support after launch. Time is logged in the firm's PSA against project and task codes, and SOWs live in its contract tool.

Fixed fee matters for what follows. Microsoft's Project Operations documentation describes the general difference: time and material lines can carry a not-to-exceed limit that caps revenue, while a fixed-price line carries a value that does not move with costs incurred. On fixed-fee work, unplanned hours show up as effort with no revenue behind it, which is exactly what makes this case hard to see. Time and materials vs managed services covers the commercial side of that choice.

The case, step by step

Each step names the record that captured it. Read down the last column: that is the evidence chain.

StepDateWhat happenedRecord createdSystem
1Feb 3SOW version 2 signed: build plus 120 hours of handover supportSigned SOW, version 2Contract tool
2Mar 11Client asks: "Could your analyst also refresh the weekly sales dashboard? Should be quick."Email with no project or task codeEmail
3Mar 12 to May 30Analyst logs 6 hours a week (72 hours in all) to the handover support taskApproved weekly time entriesPSA
4Jun 2Project manager sees handover hours at 112 of 120 with two months leftBudget reportPSA
5Jun 4Change request CR-07 raised: weekly refresh as a recurring service, 6 hours a weekChange request with scope and hoursPSA
6Jun 9Delivery director approves; account lead agrees to absorb the 72 hours already worked as goodwillApproval with written commentPSA
7Jun 16SOW version 3 signed, adding the refresh at a monthly fee from JulySigned SOW, version 3Contract tool
8Sep 30Quarterly review notes the client renewed the refresh serviceReview noteCRM

Step 3 is where the creep hides. The time entries went through normal approval: in a system like Project Operations, team members submit entries and project approvers approve them, and rejected entries come back for correction. Each week's 6 hours was approved because it was logged to a legitimate task. Nothing in the time record says the work was out of scope.

Who decided what

The case turns on three decisions, made by three different people. This table separates them.

DecisionWho made itWhat they decidedWhere it was recordedWhat would be lost without it
Say yes to the favorAnalyst, informallyDo the refresh without raising itNowhere; implied by time entriesThe start of the exception
Name the exceptionProject managerTreat the refresh as out of scopeChange request CR-07The link between hours and request
AdjudicateDelivery director with account leadAbsorb 72 past hours; bill future hoursApproval comment on CR-07The reasoning behind the outcome
Contract the outcomeClient and firmAdd a recurring monthly serviceSOW version 3The commercial result

The June 9 comment is the record that matters most. The director split one problem into two: past hours written off as goodwill, future hours billed. Without the March email and the June comment, the history shows only a support task that ran over and an unrelated amendment.

Why this sequence is useful evidence

A case like this is valuable because it captures judgment under commercial pressure, with the outcome checked months later. Four properties make it useful rather than merely complete:

  • A clear baseline. SOW version 2 states what was promised, so the exception can be measured against it.
  • A visible trigger. The budget report on June 2 shows how the firm noticed, not just that it did.
  • A reasoned decision. The approval comment explains the split, which a bare approval flag would not.
  • A checked result. The September renewal shows the decision held up with the client.

Microsoft's project-to-profit guidance treats processing project change requests as a step of its own, next to estimating, negotiating and maintaining contracts. That matches what this case shows: the change request is the hinge record, and firms that kept it with its comment have adjudication history; firms that approved by phone have only hours and amendments. The exception workflows guide draws the same line for purchasing, and the accounts payable exception process shows it in finance.

How to recognize similar cases at a client

A PSA consultant does not need to open a single record to spot this pattern. Listen for these signals:

  1. Support or handover tasks that regularly run over budget on fixed-fee work.
  2. Change requests raised late in a project, after hours were already spent.
  3. Goodwill write-offs mentioned in project reviews or margin discussions.
  4. SOW amendments that add recurring services to project engagements.
  5. A delivery director who can tell the story of a specific case from memory, which suggests the decision was discussed and probably written down.

Then ask, at metadata level: roughly how many change requests a year, how many were absorbed versus billed, whether approvals carry comments, and how many years the PSA and contract tool cover. The data scope worksheet gives the firm a format for those counts, and the system map shows which identifiers join the records across tools.

Rights sit above the delivery director. SOWs and client emails usually carry confidentiality terms, so counsel decides what could ever be licensed and what would need removing or de-identifying first; the who-can-license page names the executive. The introduced company needs 50+ full-time employees at peak (contractors excluded), a documented operating history, rights to license the records and an authorized contact. Companies in the U.S., Canada and the EU qualify, as do companies in the UK, Australia, New Zealand, India, Singapore, South Africa, Latin America, the UAE and Saudi Arabia when at least 90% of the data is in English. Unknown until SourceX reviews it: buyer interest, the rights review result and any terms. Partners sign the Channel Partner Agreement before submitting introductions, and the first valid introduction within the 90-day window is credited when the company submits a verified application. The referral brief template turns the counts into a note.

Next step

Refer a company. Earn up to $100,000. Default reward: 25% of Actual Supplier Payout, capped at $100,000 cumulatively per referred company. Eligibility and payment conditions apply, and a signed Schedule A or addendum can differ. A lead, meeting or signature alone does not trigger payment.

If a client's delivery director can point to change requests that carry the reason for each absorb-or-bill decision, register as a partner, check the firm on who qualifies and read the program terms before you suggest an introduction.

  1. Step 1Share your linkSend your personal link to a company you know.
  2. Step 2Company appliesThe company applies itself at /apply.
  3. Step 3Company signs and is paidThe company signs, delivers its data and is paid by SourceX under its agreement.
  4. Step 4You get your rewardYour 25% of the actual supplier payout. A reward becomes payable after SourceX has paid the referred company under its signed agreement and the payout conditions in the program terms are met, including finance approval and your tax and payment details.

Common questions

Is a written-off goodwill decision really useful evidence?

Yes. A decision to absorb work shows where the firm drew the line and why, which is as informative as a decision to bill. It only helps if the reason was written down next to the approval.

What if the firm never raised a change request and simply kept doing the work?

Then the history shows creep without adjudication: hours rising against a task with no decision record. That is still worth counting, but it is weaker evidence than a case with a named decision.

Do partners need to see the change requests to judge a case like this?

No. Ask whether each record in the chain exists and where. The delivery director can answer from memory or a count, without sharing a single file.

Sources

  1. learn.microsoft.com/en-us/dynamics365/project-operations/time/ti…
  2. learn.microsoft.com/en-us/dynamics365/guidance/business-processe…
  3. learn.microsoft.com/en-us/dynamics365/project-operations/pro/sal…
  4. refer.sourcex.si/terms

Free resources

Know a company with valuable proprietary data?

Become a referral partner, get your link and introduce the company’s CEO (in an owner-run company, usually the owner). Referral partners can join from most countries. We can't work with partners in countries or regions under U.S. sanctions or on U.S. restricted-party lists. The companies you introduce should be based in the U.S., Canada and the EU, or in the UK, Australia, New Zealand, India, Singapore, South Africa, Latin America, the UAE and Saudi Arabia with at least 90% of their data in English.

Refer a company →

I own a business

Explore licensing your company's data directly to SourceX for AI training and evaluation. Start a short assessment; no uploads needed.

Start an assessment